What is Pre-Production Meeting (PPM)?
What is
Pre-Production Meeting (PPM)?
A Pre-Production Meeting is known as PPM or PP meeting in
garments industry. In This meeting discuss about all important issues related
to bulk production. So that respective participants can ensure products quality
and successful shipment of ordered goods. In the pre-production meeting what
type of precautionary measures that need to be taken by the company is being
set. A pre-production meeting is basically an important meeting before starting
bulk production to set required parameter and core discussion for production to
be done. This definition for all about
garments industry.
Procedure of PPM (Pre-Production
Meeting)
To conduct a Pre-Production Meeting, Need to make a meeting
plan. In the meantime IE Person have to make layout. In the meeting need to
review Pre-Production Sample (PPS), Size Set Sample (SSS). Discuss all about
the processes parameter with all section who are participating at that meeting.
Review All Checklist of PPM. To Giving Special instruction and comment for the
bulk production. Should be find out all construction structural defects of PPS,
SSS. Need to talk about all type of machine attachment, guide, etc which is
required. IE person also talk about process and smv which is required, and
which is not required. And everybody should note down all thing what has
discuss in the meeting. Before finish the meeting need review all thing which
has discuss. And merchandiser should confirm that all required item are already
in-house and store person has to ensure, those information right or wrong which
is given by merchandiser.
PPM Meeting
Participant’s List.
- Buying QC
- IE Concern Person.
- Planning Concern Person
- Merchandiser
- Production Concern Person.
- Quality Concern Person.
- Sample Concern Person.
- Cutting Concern Person.
- Finishing Concern Person.
- Maintenance Concern
Person.
- Technician Concern Person.
- Store Concern Person.
PPM Conduct by
Buying QC and IE Person.
Arrange By
Merchandiser & Quality Concern.
Required Materials to
conduct PPM (Pre-Production Meeting)
- Buying file.
- PPS (Pre-Production Sample )
- Need to collect P.O/ order sheet.
- Cutting report.
- Sewing workment Sheet.
- Measurement & Fitting Report
- Safety Issue Report. (Pull test etc.)
- Size set report.
- Packing Direction Report.
- Inventory Report.
THE OBJECTIVE OF THE
PRE-PRODUCTION MEETING (PPM) .
- Review all PO
details, development, manufacturing necessity and standard to follow in
production before mass cutting.
- Review and
checking all the material quality to ensure they can meet the necessity.
- List down all
production issues with team and create blue print of solutions before
starting bulk production.
- Examine all
pending raw material issues and make a plan with target in-house date
which should be regularly followed.
- List the quality
checking points based on the quality control required.
- All potential
making issues are examined and need to advise best corrective plan.
- Validate time
required to deliver quality product based on the production capacity.